Multi-pad coordination

Phase H — schedule a fleet of pads against shared crews, pumps, and sand silos. Honors per-pad priority, pad ready times, and fleet transition cost when a resource moves between pads.

Shared fleet

Pads in fleet (2)

Coordinated schedule

complete
Total: 48.0 hCritical pad: Pad-SouthPeak crews: 2/2Peak pumps: 16/20Crew move lockout: 60 min
PadPriorityReady [min]StagesFinish [h]% of critical
Pad-North103224.050%
Pad-South002448.0100%
Pad-North
Pad-South
0 h24.0 h48.0 h

Honest scope: greedy priority-first event-driven scheduler. Does not solve the NP-hard global optimum — pairs well with per-pad tuning via the surrogate pad auto-tuner before coordination.