Operate
Pad operations control
Live channels belong on Frac van live. This page is the shift-level view above it: every stage on the pad reconciled against its design — placed proppant and fluid, average rate, pressure headroom, cycle time and logged downtime — rolled up into pad pace, projected finish, and non-productive time by reason. Each deviation carries the response steps a supervisor can work through, and both tables export to CSV for the daily pad report.
Pad status
- Stages complete
- 3/10
- 30% of pad · 1 aborted
- Pace
- 7.8 stages/day
- 186 min observed cycle
- Projected remaining
- 18.6 h
- At the observed cycle, not the design clock
- Non-productive time
- 15.1%
- 126 min of consumed clock
- Schedule
- On pace
- Consumed clock vs design clock on started stages
- Placed vs design
- 97% prop · 100% fluid
- Completed stages only
Stage ledger — plan vs actual
| Stage | Status | Pump min | Turnaround min | Downtime min | Reason | Proppant lb | Rate bpm | Peak psi | Placed | Cycle | Severity |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Snark 3H · 1 | / 105 | 100% | 160 min | ok | |||||||
| Snark 3H · 2 | / 105 | 91% | 215 min | action | |||||||
| Snark 3H · 3 | / 105 | 47% | 174 min | action | |||||||
| Snark 3H · 4 | / 105 | 43% | 103 min | ok | |||||||
| Snark 3H · 5 | / 105 | — | — | ok | |||||||
| Snark 4H · 1 | / 105 | 100% | 182 min | watch | |||||||
| Snark 4H · 2 | / 105 | — | — | ok | |||||||
| Snark 4H · 3 | / 105 | — | — | ok | |||||||
| Snark 4H · 4 | / 105 | — | — | ok | |||||||
| Snark 4H · 5 | / 105 | — | — | ok |
Pump minutes show actual / design. Cycle time is pump + turnaround + downtime, compared against the design clock for that stage.
Downtime by reason
- Screen-out recovery58 min · 46% · 1 stage(s)
- Sand supply42 min · 33% · 1 stage(s)
- Wireline / perforating26 min · 21% · 1 stage(s)
Deviations & response playbooks
- watchProppant shortfall — Snark 3H stage 2
Placed 91.1% of design proppant.
- Confirm the blender totalizer against the sand-coordinator ticket before crediting the stage.
- Check screen-out / pressure-limit history on the stage — placement loss usually pairs with one.
- Carry the shortfall into the next stage design only if the wellbore is clean; otherwise re-design the diversion.
- watchRate below design — Snark 3H stage 2
Average slurry rate held 92.9% of the designed rate.
- Verify online pump count and any unit derate before treating it as a formation response.
- Compare surface pressure at the reduced rate — pressure-limited vs equipment-limited changes the fix.
- If formation-limited, re-cut the rate schedule and update the treating-pressure forecast for the remaining stages.
- actionStage cycle overrun — Snark 3H stage 2
Stage cycle 134.4% of design clock (215 min consumed, 42 min downtime).
- Split the overrun into pump, wireline and downtime before assigning it to a crew.
- Re-time the remaining stage plan with the observed cycle so the pad ETA stays honest.
- Escalate to the pad coordinator if the overrun is repeating on the same crew change.
- actionRate below design — Snark 3H stage 3
Average slurry rate held 84.7% of the designed rate.
- Verify online pump count and any unit derate before treating it as a formation response.
- Compare surface pressure at the reduced rate — pressure-limited vs equipment-limited changes the fix.
- If formation-limited, re-cut the rate schedule and update the treating-pressure forecast for the remaining stages.
- actionPressure near limit — Snark 3H stage 3
Peak treating pressure reached 98.3% of max allowable.
- Hold rate and confirm the max allowable against the wellhead / casing rating in the job program.
- Step down rate and log the step-down response — it doubles as near-wellbore friction data.
- If the limit repeats, add friction reducer or perf-friction relief before the next stage rather than derating mid-stage.
- watchStage cycle overrun — Snark 4H stage 1
Stage cycle 113.8% of design clock (182 min consumed, 26 min downtime).
- Split the overrun into pump, wireline and downtime before assigning it to a crew.
- Re-time the remaining stage plan with the observed cycle so the pad ETA stays honest.
- Escalate to the pad coordinator if the overrun is repeating on the same crew change.
- watchDowntime concentrated in screen-out recovery
Screen-out recovery owns 46% of pad downtime (58 min over 1 stage(s)).
- Open a single-cause review on the dominant reason code rather than spreading the fix.
- Confirm the logistics or maintenance owner and set a next-shift commitment.
- Track the reason on the daily pad report until its share drops below the callout threshold.
Live stage projection
Snark 3H stage 3 is pumping. Placement pace is extrapolated to the end of the stage so a shortfall is called while there is still stage left to fix it.
Watch: Projected proppant 91% of design
- Projected pump time
- 112 min
- +7 min vs design
- Projected proppant
- 400,000 lb
- 91% of design
- Rate adherence
- 95%
- 81 of 85 bpm
- Pressure headroom
- 92%
- limit 10,500 psi
- • Projected proppant 91% of design
- • Surface pressure at 92% of max allowable
Pad finish forecast
5 of 5 stages left · 12.5 h remaining at 160 min/stage · On the design clock.
Assurance layer
Every deviation carries a named acknowledgement and, at action severity, an engineer approval before the pad moves on. Alongside it: offset-well gauge response during pumping classified into trend versus frac hit, and per-feed ingest health that is graded on cadence and completeness rather than on which vendor sent it.
Next-stage assurance gate
- • 2 action-severity deviations without engineer sign-off.
- • 1 offset well in frac-hit response.
Deviation acknowledgement & approval
Open
2
Overdue
2
Mean time to ack
7 min
Approval gaps
0
| Finding | Severity | Age | Status | Needs | Last signature | Sign |
|---|---|---|---|---|---|---|
| Proppant shortfall — Snark 3H stage 3 | action | 115 min | acknowledged | engineer | R. Diaz — Flushed and swapped to 40/70 for the tail-in. | |
| Pressure near limit — Snark 3H stage 4 | watch | 32 min (overdue) | open | supervisor | — | |
| Rate below design — Snark 4H stage 2 | action | 19 min (overdue) | open | engineer | — |
Action-severity deviations need engineer sign-off; watch-level needs a supervisor. Closing below that level is recorded as an approval gap rather than silently accepted.
Offset-well monitoring during pumping
1 offset well showing frac-hit response — intervene before the next stage.
| Offset well | Spacing | Rise | Rate | Per 1,000 ft | Response | Recommended action |
|---|---|---|---|---|---|---|
| Snark 1H | 880 ft | 225 psi | 185 psi/hr | 255.68 psi | frac-hit | Frac hit on Snark 1H — shut in or choke back the offset, drop stage rate, and cut proppant concentration before continuing. |
| Snark 2H | 1650 ft | 58 psi | 34 psi/hr | 35.15 psi | pressure-trend | Pressure trend on Snark 2H — keep the gauge on a 1-minute scan, flag the next two stages, and pre-stage a rate step-down. |
| Snark 5H | 2620 ft | 2 psi | 1 psi/hr | 0.76 psi | no-response | No measurable response on Snark 5H — continue as designed and keep monitoring. |
Vendor-neutral ingestion status
Live feeds
3/5
Degraded
1
Completeness
98.5%
Vendors / protocols
4 / 4
| Channel | Vendor | Protocol | Health | Sample age | Complete | Note |
|---|---|---|---|---|---|---|
| Chemical totals | Chem Vendor C | CSV drop | stale | 1800s | 77.8% | Planned outage — excluded from ingest trust. |
| Offset gauge pressure | Gauge Vendor B | MQTT | stale | 46s | 90.7% | Behind by 4.6× cadence at 90.7% completeness. |
| Slurry rate | Pumper Data Co | WITSML | live | 3s | 98.5% | On cadence, 98.5% complete. |
| Treating pressure | Pumper Data Co | WITSML | live | 2s | 100% | On cadence, 100% complete. |
| Disclosure records | FracFocus | FracFocus | live | 240s | 100% | On cadence, 100% complete. |