Wellbore Genius
Help

Operate

Pad operations control

Live channels belong on Frac van live. This page is the shift-level view above it: every stage on the pad reconciled against its design — placed proppant and fluid, average rate, pressure headroom, cycle time and logged downtime — rolled up into pad pace, projected finish, and non-productive time by reason. Each deviation carries the response steps a supervisor can work through, and both tables export to CSV for the daily pad report.

Pad status

Stages complete
3/10
30% of pad · 1 aborted
Pace
7.8 stages/day
186 min observed cycle
Projected remaining
18.6 h
At the observed cycle, not the design clock
Non-productive time
15.1%
126 min of consumed clock
Schedule
On pace
Consumed clock vs design clock on started stages
Placed vs design
97% prop · 100% fluid
Completed stages only

Stage ledger — plan vs actual

StageStatusPump minTurnaround minDowntime minReasonProppant lbRate bpmPeak psiPlacedCycleSeverity
Snark 3H · 1/ 105100%160 min
ok
Snark 3H · 2/ 10591%215 min
action
Snark 3H · 3/ 10547%174 min
action
Snark 3H · 4/ 10543%103 min
ok
Snark 3H · 5/ 105
ok
Snark 4H · 1/ 105100%182 min
watch
Snark 4H · 2/ 105
ok
Snark 4H · 3/ 105
ok
Snark 4H · 4/ 105
ok
Snark 4H · 5/ 105
ok

Pump minutes show actual / design. Cycle time is pump + turnaround + downtime, compared against the design clock for that stage.

Downtime by reason

  • Screen-out recovery58 min · 46% · 1 stage(s)
  • Sand supply42 min · 33% · 1 stage(s)
  • Wireline / perforating26 min · 21% · 1 stage(s)

Deviations & response playbooks

  • watch
    Proppant shortfall — Snark 3H stage 2

    Placed 91.1% of design proppant.

    1. Confirm the blender totalizer against the sand-coordinator ticket before crediting the stage.
    2. Check screen-out / pressure-limit history on the stage — placement loss usually pairs with one.
    3. Carry the shortfall into the next stage design only if the wellbore is clean; otherwise re-design the diversion.
  • watch
    Rate below design — Snark 3H stage 2

    Average slurry rate held 92.9% of the designed rate.

    1. Verify online pump count and any unit derate before treating it as a formation response.
    2. Compare surface pressure at the reduced rate — pressure-limited vs equipment-limited changes the fix.
    3. If formation-limited, re-cut the rate schedule and update the treating-pressure forecast for the remaining stages.
  • action
    Stage cycle overrun — Snark 3H stage 2

    Stage cycle 134.4% of design clock (215 min consumed, 42 min downtime).

    1. Split the overrun into pump, wireline and downtime before assigning it to a crew.
    2. Re-time the remaining stage plan with the observed cycle so the pad ETA stays honest.
    3. Escalate to the pad coordinator if the overrun is repeating on the same crew change.
  • action
    Rate below design — Snark 3H stage 3

    Average slurry rate held 84.7% of the designed rate.

    1. Verify online pump count and any unit derate before treating it as a formation response.
    2. Compare surface pressure at the reduced rate — pressure-limited vs equipment-limited changes the fix.
    3. If formation-limited, re-cut the rate schedule and update the treating-pressure forecast for the remaining stages.
  • action
    Pressure near limit — Snark 3H stage 3

    Peak treating pressure reached 98.3% of max allowable.

    1. Hold rate and confirm the max allowable against the wellhead / casing rating in the job program.
    2. Step down rate and log the step-down response — it doubles as near-wellbore friction data.
    3. If the limit repeats, add friction reducer or perf-friction relief before the next stage rather than derating mid-stage.
  • watch
    Stage cycle overrun — Snark 4H stage 1

    Stage cycle 113.8% of design clock (182 min consumed, 26 min downtime).

    1. Split the overrun into pump, wireline and downtime before assigning it to a crew.
    2. Re-time the remaining stage plan with the observed cycle so the pad ETA stays honest.
    3. Escalate to the pad coordinator if the overrun is repeating on the same crew change.
  • watch
    Downtime concentrated in screen-out recovery

    Screen-out recovery owns 46% of pad downtime (58 min over 1 stage(s)).

    1. Open a single-cause review on the dominant reason code rather than spreading the fix.
    2. Confirm the logistics or maintenance owner and set a next-shift commitment.
    3. Track the reason on the daily pad report until its share drops below the callout threshold.

Live stage projection

Snark 3H stage 3 is pumping. Placement pace is extrapolated to the end of the stage so a shortfall is called while there is still stage left to fix it.

Watch

Watch: Projected proppant 91% of design

Stage progress (fluid placed)52%
Projected pump time
112 min
+7 min vs design
Projected proppant
400,000 lb
91% of design
Rate adherence
95%
81 of 85 bpm
Pressure headroom
92%
limit 10,500 psi
  • Projected proppant 91% of design
  • Surface pressure at 92% of max allowable

Pad finish forecast

5 of 5 stages left · 12.5 h remaining at 160 min/stage · On the design clock.

Assurance layer

Every deviation carries a named acknowledgement and, at action severity, an engineer approval before the pad moves on. Alongside it: offset-well gauge response during pumping classified into trend versus frac hit, and per-feed ingest health that is graded on cadence and completeness rather than on which vendor sent it.

Next-stage assurance gate

2 blocker(s)
  • 2 action-severity deviations without engineer sign-off.
  • 1 offset well in frac-hit response.

Deviation acknowledgement & approval

Open

2

Overdue

2

Mean time to ack

7 min

Approval gaps

0

FindingSeverityAgeStatusNeedsLast signatureSign
Proppant shortfall — Snark 3H stage 3
action
115 minacknowledgedengineerR. Diaz — Flushed and swapped to 40/70 for the tail-in.
Pressure near limit — Snark 3H stage 4
watch
32 min (overdue)opensupervisor
Rate below design — Snark 4H stage 2
action
19 min (overdue)openengineer

Action-severity deviations need engineer sign-off; watch-level needs a supervisor. Closing below that level is recorded as an approval gap rather than silently accepted.

Offset-well monitoring during pumping

1 offset well showing frac-hit response — intervene before the next stage.

Offset wellSpacingRiseRatePer 1,000 ftResponseRecommended action
Snark 1H880 ft225 psi185 psi/hr255.68 psi
frac-hit
Frac hit on Snark 1H — shut in or choke back the offset, drop stage rate, and cut proppant concentration before continuing.
Snark 2H1650 ft58 psi34 psi/hr35.15 psi
pressure-trend
Pressure trend on Snark 2H — keep the gauge on a 1-minute scan, flag the next two stages, and pre-stage a rate step-down.
Snark 5H2620 ft2 psi1 psi/hr0.76 psi
no-response
No measurable response on Snark 5H — continue as designed and keep monitoring.

Vendor-neutral ingestion status

Live feeds

3/5

Degraded

1

Completeness

98.5%

Vendors / protocols

4 / 4

ChannelVendorProtocolHealthSample ageCompleteNote
Chemical totalsChem Vendor CCSV dropstale1800s77.8%Planned outage — excluded from ingest trust.
Offset gauge pressureGauge Vendor BMQTTstale46s90.7%Behind by 4.6× cadence at 90.7% completeness.
Slurry ratePumper Data CoWITSMLlive3s98.5%On cadence, 98.5% complete.
Treating pressurePumper Data CoWITSMLlive2s100%On cadence, 100% complete.
Disclosure recordsFracFocusFracFocuslive240s100%On cadence, 100% complete.