Wellbore Genius
What the well path costs
$4.63 MM of capital on 8,975 ft of hole — $2,314 per lateral foot, $578,600 per stage and $96,433 per cluster.
Oil price: saved value on this device (no live quote recorded). The CSV starts with the same header block as the well budget export, then adds the path section.
Cost per lateral foot
$2,314
2,000 ft of completed lateral
Capital per drilled foot
$516
8,975 ft total measured depth
Cost per stage
$578,600
8 stages on the path
Cost per cluster
$96,433
48 clusters
The hole this budget follows
No survey is loaded, so the plan's landing depth, lateral length and azimuth generate a designed path. Lateral starts at 6,975 ft MD and lands at 6,566 ft TVD.
Drilling
$2.39 MM
$267 per drilled ft
Completion
$1.35 MM
Equipment
$0.88 MM
Operating window
$1.43 MM
120 months
Spend by stage, on measured depth
Stage 1 is at the toe, the order the job is pumped. The money is the well budget's capital per stage; the path supplies the depth.
| Stage | MD interval | Midpoint MD | Midpoint TVD | Clusters | Stage capital | Per cluster |
|---|---|---|---|---|---|---|
| Stage 1 | 8,838–8,993 ft | 8,945 ft | 6,566 ft | 6 | $578,600 | $96,433 |
| Stage 2 | 8,588–8,802 ft | 8,695 ft | 6,566 ft | 6 | $578,600 | $96,433 |
| Stage 3 | 8,338–8,552 ft | 8,445 ft | 6,566 ft | 6 | $578,600 | $96,433 |
| Stage 4 | 8,088–8,302 ft | 8,195 ft | 6,566 ft | 6 | $578,600 | $96,433 |
| Stage 5 | 7,838–8,052 ft | 7,945 ft | 6,566 ft | 6 | $578,600 | $96,433 |
| Stage 6 | 7,588–7,802 ft | 7,695 ft | 6,566 ft | 6 | $578,600 | $96,433 |
| Stage 7 | 7,338–7,552 ft | 7,445 ft | 6,566 ft | 6 | $578,600 | $96,433 |
| Stage 8 | 7,088–7,302 ft | 7,195 ft | 6,566 ft | 6 | $578,600 | $96,433 |
- No deviation survey imported, so this is a designed path: vertical hole, a 8.0°/100 ft curve to horizontal, then 2,000 ft of lateral on 90°. It matches the plan's landing depth, but it is a design, not a measurement.
- 8 stages × 6 clusters = 48 perforation clusters, from 7,106 to 8,975 ft MD (6,566–6,566 ft TVD).
- Wellhead elevation is 0, so subsea depth equals true vertical depth. Enter the pad elevation and surface coordinates to land the path in your model's own grid space.
- Costs keep the well budget's rates; the designed path only locates the stages and clusters.