Pad drilling and completion schedule
When this pad gets built. Drilling time comes from the lateral the plan needs, completion time from its own stage count and perforation clusters, so tightening the spacing or adding clusters moves the dates. Set the wells, the rigs and the crews and the whole timeline redraws.
Starting numbers — no plan solved yet
4 wells
32 stages
192 clusters
1 rig · 1 crew
The timeline
4 wells take 97 days: last frac 2026-12-23, last well on production 2027-01-06.
Days start to finish
97
First well on production
Dec 23, 2026
Last frac finished
Dec 23, 2026
Last well on production
Jan 6, 2027
Rig days
59.3
Crew days
18.5
Hours a stage takes
5.9 h
Stages a crew places a day
3.1
Rig move / rig upDrillingCrew moveCompletionDrill-out and flowback
- Drilling is 9 days of vertical and curve plus 2,000 ft of lateral at 1,100 ft a day.
- A stage takes 5.9 hours — 3.2 pumping plus 6 clusters at 0.45 hours each — so a crew places 3.1 stages a day.
- Every frac waits until the whole pad is drilled, so no rig is working next door.
Well by well
Each well’s rig, crew, stages and the four dates that matter.
| Well | Rig | Crew | Stages | Clusters | Drill days | Frac days | Spud | Rig release | Frac done | On production |
|---|---|---|---|---|---|---|---|---|---|---|
| Pad plan well #1 | Rig 1 | Crew 1 | 8 | 48 | 10.8 | 2.6 | Oct 5, 2026 | Oct 16, 2026 | Dec 9, 2026 | Dec 23, 2026 |
| Pad plan well #2 | Rig 1 | Crew 1 | 8 | 48 | 10.8 | 2.6 | Oct 20, 2026 | Oct 31, 2026 | Dec 14, 2026 | Dec 28, 2026 |
| Pad plan well #3 | Rig 1 | Crew 1 | 8 | 48 | 10.8 | 2.6 | Nov 4, 2026 | Nov 14, 2026 | Dec 18, 2026 | Jan 1, 2027 |
| Pad plan well #4 | Rig 1 | Crew 1 | 8 | 48 | 10.8 | 2.6 | Nov 18, 2026 | Nov 29, 2026 | Dec 23, 2026 | Jan 6, 2027 |
Rigs, crews and pace
The assumptions behind the dates. They are remembered between sessions.
0.75 means 18 pumping hours a day
The well count, stage spacing and cluster design come from the pad plan, and the same well count prices the cost estimator.