Pad drilling and completion schedule

When this pad gets built. Drilling time comes from the lateral the plan needs, completion time from its own stage count and perforation clusters, so tightening the spacing or adding clusters moves the dates. Set the wells, the rigs and the crews and the whole timeline redraws.

Starting numbers — no plan solved yet
4 wells
32 stages
192 clusters
1 rig · 1 crew
The timeline
4 wells take 97 days: last frac 2026-12-23, last well on production 2027-01-06.
Days start to finish
97
First well on production
Dec 23, 2026
Last frac finished
Dec 23, 2026
Last well on production
Jan 6, 2027
Rig days
59.3
Crew days
18.5
Hours a stage takes
5.9 h
Stages a crew places a day
3.1
Oct 1, 2026Oct 31, 2026Nov 30, 2026Dec 30, 2026Pad plan well #1Pad plan well #1 — Rig move / rig up: 2026-10-01 → 2026-10-05Pad plan well #1 — Drilling: 2026-10-05 → 2026-10-16Pad plan well #1 — Crew move: 2026-12-04 → 2026-12-06Pad plan well #1 — Completion: 2026-12-06 → 2026-12-09Pad plan well #1 — Drill-out and flowback: 2026-12-09 → 2026-12-23Pad plan well #2Pad plan well #2 — Rig move / rig up: 2026-10-16 → 2026-10-20Pad plan well #2 — Drilling: 2026-10-20 → 2026-10-31Pad plan well #2 — Crew move: 2026-12-09 → 2026-12-11Pad plan well #2 — Completion: 2026-12-11 → 2026-12-14Pad plan well #2 — Drill-out and flowback: 2026-12-14 → 2026-12-28Pad plan well #3Pad plan well #3 — Rig move / rig up: 2026-10-31 → 2026-11-04Pad plan well #3 — Drilling: 2026-11-04 → 2026-11-14Pad plan well #3 — Crew move: 2026-12-14 → 2026-12-16Pad plan well #3 — Completion: 2026-12-16 → 2026-12-18Pad plan well #3 — Drill-out and flowback: 2026-12-18 → 2027-01-01Pad plan well #4Pad plan well #4 — Rig move / rig up: 2026-11-14 → 2026-11-18Pad plan well #4 — Drilling: 2026-11-18 → 2026-11-29Pad plan well #4 — Crew move: 2026-12-18 → 2026-12-20Pad plan well #4 — Completion: 2026-12-20 → 2026-12-23Pad plan well #4 — Drill-out and flowback: 2026-12-23 → 2027-01-06
Rig move / rig upDrillingCrew moveCompletionDrill-out and flowback
  • Drilling is 9 days of vertical and curve plus 2,000 ft of lateral at 1,100 ft a day.
  • A stage takes 5.9 hours — 3.2 pumping plus 6 clusters at 0.45 hours each — so a crew places 3.1 stages a day.
  • Every frac waits until the whole pad is drilled, so no rig is working next door.
Well by well
Each well’s rig, crew, stages and the four dates that matter.
WellRigCrewStagesClustersDrill daysFrac daysSpudRig releaseFrac doneOn production
Pad plan well #1Rig 1Crew 184810.82.6Oct 5, 2026Oct 16, 2026Dec 9, 2026Dec 23, 2026
Pad plan well #2Rig 1Crew 184810.82.6Oct 20, 2026Oct 31, 2026Dec 14, 2026Dec 28, 2026
Pad plan well #3Rig 1Crew 184810.82.6Nov 4, 2026Nov 14, 2026Dec 18, 2026Jan 1, 2027
Pad plan well #4Rig 1Crew 184810.82.6Nov 18, 2026Nov 29, 2026Dec 23, 2026Jan 6, 2027
Rigs, crews and pace
The assumptions behind the dates. They are remembered between sessions.

0.75 means 18 pumping hours a day

The well count, stage spacing and cluster design come from the pad plan, and the same well count prices the cost estimator.